At 30 September 2026, connection requests to Italy's transmission grid handled by Terna came to 309.6 GW for renewable plants (5,637 requests), 285.6 GW for storage and 121.7 GW for consumers, of which 109.0 GW were data centres. Of the 139.7 GW of solar requested, 10.3 GW (230 requests) had reached the most advanced stage, STMD or contracts ("STMD/Contratti").
Figures last updated: · Terna data at 30 September 2026 · Also in Italian: Richieste di connessione a Terna: rinnovabili, accumuli e data center in numeri
| Type of request | Requests | Capacity (GW) |
|---|---|---|
| Renewables | 5,637 | 309.6 |
| Storage | 3,461 | 285.6 |
| Consumers | 916 | 121.7 |
The total is 716.8 GW. Terna handles high and extra-high voltage connections of plants of 10 MW or more, so requests to the distribution grid are not in these figures. The capacity is that of the requests: it measures demand for connection, not the capacity that will actually be built.
Terna puts every request in one of five stages. They run from the general minimum technical solution for connection (STMG) awaiting acceptance to the detailed minimum technical solution (STMD) and contracts. The abbreviations come from ARERA's integrated text on active connections (TICA).
| Stage of the request | Renewables (GW) | Storage (GW) | Consumers (GW) |
|---|---|---|---|
| STMG to be accepted | 31.3 | 43.6 | 39.3 |
| STMG accepted | 115.0 | 82.9 | 72.5 |
| Projects under evaluation | 47.3 | 58.4 | 5.0 |
| Projects with clearance (nulla osta) | 102.9 | 88.8 | 0.1 |
| STMD or contracts | 13.0 | 12.0 | 4.8 |
The STMD or contracts stage holds 13.0 GW of renewables and 12.0 GW of storage, a small fraction of all requests.
| Source | Requests | Capacity (GW) |
|---|---|---|
| Solar | 3,506 | 139.7 |
| Onshore wind | 2,001 | 104.0 |
| Offshore wind | 94 | 63.6 |
| Hydro | 19 | 1.9 |
| Biomass | 12 | 0.3 |
| Geothermal | 5 | 0.1 |
| Type | Requests | Capacity (GW) |
|---|---|---|
| Standalone storage | 2,305 | 253.6 |
| Co-located with solar | 822 | 16.4 |
| Co-located with wind | 310 | 8.3 |
| Pure pumped hydro | 19 | 5.8 |
| Mixed pumped hydro | 5 | 1.4 |
Standalone storage alone accounts for 253.6 GW (2,305 requests).
Of the 121.7 GW requested by consumers, 109.0 GW (586 requests) are data centres. The region with the most is Lombardy, with 49.3 GW.
| Stage of the request | Requests | Capacity (GW) |
|---|---|---|
| STMG to be accepted | 198 | 38.3 |
| STMG accepted | 362 | 64.8 |
| Projects under evaluation | 10 | 4.0 |
| Projects with clearance (nulla osta) | 0 | 0.0 |
| STMD or contracts | 16 | 1.9 |
| Region | Renewables (GW) | Storage (GW) | Consumers (GW) | of which data centres (GW) |
|---|---|---|---|---|
| Apulia | 90.0 | 74.5 | 9.8 | 8.5 |
| Sicily | 67.0 | 47.4 | 3.9 | 2.6 |
| Lombardy | 4.1 | 18.4 | 51.8 | 49.3 |
| Sardinia | 44.5 | 21.1 | 1.1 | 1.0 |
| Basilicata | 22.1 | 20.9 | 0.5 | 0.3 |
| Lazio | 12.9 | 15.8 | 13.5 | 12.7 |
| Piedmont | 4.1 | 12.6 | 16.1 | 15.2 |
| Emilia-Romagna | 10.5 | 13.3 | 7.0 | 6.4 |
| Campania | 10.4 | 16.6 | 1.5 | 1.2 |
| Veneto | 6.5 | 7.6 | 8.3 | 7.4 |
| Calabria | 11.1 | 8.7 | 0.5 | 0.4 |
| Tuscany | 8.6 | 7.4 | 1.6 | 0.5 |
| Molise | 8.4 | 7.2 | 0.6 | 0.3 |
| Friuli Venezia Giulia | 1.0 | 5.8 | 2.5 | 1.8 |
| Umbria | 2.5 | 3.1 | 0.7 | 0.3 |
| Abruzzo | 1.9 | 2.1 | 0.4 | 0.3 |
| Marche | 2.3 | 1.8 | 0.1 | 0.0 |
| Liguria | 1.2 | 0.2 | 0.6 | 0.2 |
| Trentino-South Tyrol | 0.2 | 0.8 | 0.2 | 0.0 |
| Aosta Valley | 0.1 | 0.0 | 0.8 | 0.8 |
For renewables the leading region is Apulia, with 90.0 GW. Regions are ranked by total capacity requested.
Quote these figures freely, with a link to this page. The HTML below holds the headline figures, their date and the source in one paragraph, ready for an article or a report.
<p>At 30 September 2026, connection requests to Italy's transmission grid handled by Terna came to 309.6 GW for renewable plants, 285.6 GW for storage and 121.7 GW for consumers, of which 109.0 GW were data centres. Source: <a href="https://ariadnelabs.eu/guides/italy-grid-connection-requests-terna.html">Ariadne Labs, grid connection requests to Terna in numbers</a>, from Terna's Econnextion data, figures of 21 October 2026.</p>Once a month, one short email with the latest figures from this page and our other data pages, and what moved. To subscribe, write to hello@ariadnelabs.eu; to stop, reply "stop". Details are in the privacy notice.
The figures on this page describe the market. For your own projects, MitOS keeps each plant's stage together with the deadlines and guarantees that come with it. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.
A short demo on the real stages of your projects, with Italian law already built in.
At 30 September 2026, 109.0 GW across 586 requests, according to Terna's Econnextion data.
On Terna's transmission grid at 30 September 2026, 5,637 requests for 309.6 GW, of which 139.7 GW were solar (3,506 requests).
STMG is the general minimum technical solution for connection, STMD the detailed minimum technical solution. The terms come from ARERA's integrated text on active connections (TICA, Annex A to resolution ARG/elt 99/08).
Whenever Terna publishes a new reference date, usually once a month.
This page presents aggregates of data published by Terna for information and does not replace legal or technical advice on a specific project. Each figure holds for the reference date given. Only the data as published by Terna are authoritative.