Guide · Italy

Italy's aree idonee: what remains and what has changed

Search for "aree idonee" today and most of what you find is out of date. The rule those pages were built on has been repealed, and the ministerial decree that set its criteria has been cut back by the administrative courts. What you actually need to know is which procedure applies now.

Last updated: · Also in Italian: Aree idonee: cosa resta e cosa è cambiato

At a glance

WhatRuleReference
Framework in forcethe Consolidated Renewables Act (Testo Unico sulle rinnovabili)Legislative Decree 190/2024
The previous aree idonee rulerepealed in November 2025, its rules moved into the new frameworkart. 20, Legislative Decree 199/2021
Current rules on onshore aree idoneeart. 11-bis, introduced by Decree-Law 175/2025 and confirmed by Law 4/2026Decree-Law 175/2025, Law 4/2026
Authorization regimesfree activity (attività libera), PAS, Autorizzazione UnicaLegislative Decree 190/2024
Simplified procedurekey time limits of 30, 45 or 60 daysLegislative Decree 190/2024
Autorizzazione Unicaservices conference within 120 daysLegislative Decree 190/2024
Aree idonee by lawa base set identified by national lawnational framework
Further aree idoneeidentified by each Region and autonomous Province by its own lawregional law

Why almost every page you find online is old

The aree idonee rules were written in 2021 and implemented by ministerial decree in June 2024. The decree was challenged before the administrative courts and partly annulled, and in the meantime the whole subject was absorbed into a Consolidated Act that reorganised it. As a result, the explanatory material online describes at least three different frameworks, often without saying which date it refers to.

So the useful question is not where a plant counts as suitable. It is which authorization regime applies to it today, and how much time that regime allows.

The three regimes, and what triggers each

The Consolidated Act distinguishes three administrative regimes. Which one applies, and with which time limits, depends on the project and on the consents it needs.

What matters for a project schedule is not the time limit itself but the fact that it does not run continuously. These time limits can be suspended when further documents, an environmental impact assessment (VIA) or an appropriate assessment (valutazione di incidenza) are needed. A time limit that is formally met can contain months of waiting.

Two levels, not one

National law identifies a base set of aree idonee by law. Each Region and autonomous Province must then identify further aree idonee by its own law, in line with national principles and renewable capacity targets.

It follows that a project's location must always be assessed on both levels: the national framework and the law of the Region where it sits. That is why two identical projects a few kilometres apart, but in different Regions, can find themselves on routes that differ by months. Where each Region stands is in the region-by-region guide.

A signal from the courts

The subject has been the object of rulings that narrowed the Regions' room for moratoria. In a ruling of March 2025, the Constitutional Court declared unconstitutional a regional law that temporarily suspended proceedings. The principle that follows, useful to developers, is that a general suspension of time limits is not an instrument the Regions have available.

How MitOS keeps the picture together

MitOS, by Ariadne Labs, derives the permitting route from the rules themselves. Change one input of the project and the route is recalculated, with each requirement carrying the legal reference it comes from. When the rules change, as they just have in Italy, the route changes, not a document someone has to remember to update. All deadlines land on the same 90-day horizon, with alerts that rise while there is still time to act.

See it on your own projects

Ask for a short, focused demo on the real stages of your projects: the permitting route, with the legal reference next to every step.

Frequently asked questions

Is article 20 of Legislative Decree 199/2021 still in force?

No. It was repealed in November 2025, and its main rules moved into the Consolidated Renewables Act (Legislative Decree 190/2024).

How long does the simplified procedure take?

The key time limits can be thirty, forty-five or sixty days, depending on the case.

How long does an Autorizzazione Unica take?

As a rule the services conference lasts one hundred and twenty days, subject to suspensions.

Who identifies the aree idonee?

Both levels: national law identifies a base set, and the Regions and autonomous Provinces identify more by their own laws.

This page summarises provisions for information and does not replace legal or permitting advice on a specific project. Only the official publication in the Gazzetta Ufficiale, regional laws and the acts of the competent administrations are authoritative.