Italy's national environmental impact assessments for PNIEC-PNRR projects: how many are open, and for how long

The environmental assessment portal of Italy's Ministry of the Environment and Energy Security (MASE) shows 1,521 national procedures still open for PNIEC-PNRR projects: 1,333 environmental impact assessments (VIA) and 188 single environmental measures (PUA). 97.8% of them concern renewable plants, and half of them started more than 3.0 years ago.

Figures last updated: · Also in Italian: VIA dei progetti PNIEC-PNRR: quante procedure sono aperte al MASE e da quanto tempo

What is still open, by type of work

Type of workOpen proceduresStated capacity (GW)Procedures stating it
Agrivoltaic68926.1598
Onshore wind58335.6553
Solar PV1695.8146
Offshore wind3815.433
Hydropower80.21
Geothermal1
Other works (roads, railways, gas and more)33

Agrivoltaic plants account for 689 procedures, onshore wind for 583, solar PV for 169 and offshore wind for 38. Where the project description states the total capacity, in 1,331 of the 1,488 renewable procedures, it adds up to 83.1 GW. That is a floor, because the other descriptions do not give one unambiguous figure. The other works are roads, railways, gas pipelines and industrial plants, which the portal also files under PNIEC-PNRR projects.

Where the procedures stand

Stage, from the portal's statusesOpen procedures
Administrative check19
Technical review by the commission1,011
Opinion issued, decision in preparation112
Awaiting the joint decision (“concerto”)123
Opinion or signature of the culture authorities9
Review of a dissent, or substitute powers21
At the Presidency of the Council of Ministers212
Suspended10
No status given4

Most of them, 1,011, are in technical review by the commission. Another 365 (24.0%) sit in one of the stages the portal labels as awaiting the joint decision ("concerto"), an opinion or signature of the culture authorities, the review of a dissent or substitute powers, or at the Presidency of the Council of Ministers, where 212 procedures are.

How long they have been open

Year startedProcedures still open
202171
2022328
2023455
2024531
2025115
202621

The median open procedure started 1,096 days ago. 1,295 procedures (85.1%) are more than two years old, and 762 (50.1%) more than three. The date is the start date the portal gives for each procedure.

Started and concluded, year by year

YearVIA startedVIA concludedPUA startedPUA concluded
20212350400
2022592191070
202363847494
20246191434815
20251712741224
202642211524

By the portal's own statistics, 2,297 VIA procedures for PNIEC-PNRR projects have started since 2021 and 694 have concluded. In 2025, 171 started and 274 concluded; so far in 2026, 42 have started and 211 have concluded. The statistics count procedures by the portal's own rule, so they do not match the count from the lists.

Procedures by region

RegionOpen proceduresof which windof which agrivoltaic and solar PV
Apulia436180245
Sardinia305122174
Sicily24486156
Basilicata18072106
Molise824138
Lazio802553
Tuscany523021
Campania372312
Calabria36295
Emilia-Romagna291015
Umbria22184
Piedmont21120
Veneto19117
Marche12102
Abruzzo1163
Lombardy1107
Liguria971
Friuli Venezia Giulia606
Trentino-South Tyrol100
At sea, no region321

Apulia comes first, with 436 open procedures. The 73 procedures that cover more than one region are counted in each, so the table adds up to more than the total.

How the figures are counted

Cite these figures

Quote these figures freely, with a link to this page. The HTML below holds the headline figures, their date and the source in one paragraph, ready for an article or a report.

<p>MASE's environmental assessment portal shows 1,521 national VIA and PUA procedures still open for Italian PNIEC-PNRR projects, 97.8% of them for renewable plants; half of them started more than 3.0 years ago. Source: <a href="https://ariadnelabs.eu/guides/italy-environmental-impact-assessment-pniec-pnrr.html">Ariadne Labs, Italy's PNIEC-PNRR environmental impact assessments in numbers</a>, from MASE data, figures of 26 October 2026.</p>

The monthly numbers, by email

Once a month, one short email with the latest figures from this page and our other data pages, and what moved. To subscribe, write to hello@ariadnelabs.eu; to stop, reply "stop". Details are in the privacy notice.

How MitOS sees it

The figures on this page describe the market. For your own projects, MitOS keeps each plant's stage together with the deadlines and guarantees that come with it. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.

See the route for your own projects

A short demo on the real stages of your projects, with Italian law already built in.

Frequently asked questions

How many PNIEC-PNRR environmental impact assessments are open in Italy?

1,333 VIA and 188 PUA, 1,521 procedures in all, according to the lists on MASE's environmental assessment portal on the date at the top.

How long have they been waiting?

Half of the open procedures started more than 3.0 years ago; 762 are more than three years old.

Which region has the most open procedures?

Apulia, with 436 open procedures on the date at the top.

How often are the figures updated?

The portal's lists are read once a week; the date at the top changes only when the figures change.

Sources

This page presents counts of data published by MASE for information and does not replace legal or technical advice on a specific project. Every figure is as of the date at the top. Only the data on MASE's portal are authoritative.