In ΡΑΑΕΥ's register, 1,580 electricity storage stations with a combined injection power of 65.3 GW hold a storage licence. On the transmission system, however, only 42 stations, 1.6 GW, had a connection offer or were operating, according to ΑΔΜΗΕ's register (edition: April 2026).
Figures last updated: · Also in Greek: Αποθήκευση ενέργειας στην Ελλάδα: η αδειοδότηση σε αριθμούς
The table follows a station from the storage licence to connection. Each figure comes from a different official file with its own date, so the date is given beside every row.
| Stage | Stations | Injection power (GW) | Capacity (GWh) | Source and date |
|---|---|---|---|---|
| Storage licence, ΡΑΑΕΥ register | 1,580 | 65.3 | 307.1 | ΡΑΑΕΥ, 20 October 2026 |
| Complete connection requests pending at ΑΔΜΗΕ | 480 | 27.5 | 80.0 | ΑΔΜΗΕ, position at 31 October 2025 |
| Connection offer or in operation, transmission system | 42 | 1.6 | 5.3 | ΑΔΜΗΕ, register of April 2026 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The gap between the rows is the finding. A storage licence does not give a place on the grid: storage obtains a Final Connection Offer on separate tracks with their own capacity caps, as the guide to the priority groups explains.
Most stations in the register are batteries: 1,473 stations, 49.8 GW. Pumped storage counts fewer stations, 123, but larger ones, with 16.7 GW in total. These figures cover every storage station in the register, whatever its stage.
| Region | Stations | Injection power (GW) | Capacity (GWh) |
|---|---|---|---|
| Central Greece | 341 | 15.6 | 66.8 |
| Western Macedonia | 235 | 12.1 | 64.4 |
| Central Macedonia | 235 | 8.4 | 46.6 |
| Thessaly | 187 | 7.7 | 24.3 |
| Eastern Macedonia and Thrace | 158 | 7.5 | 34.2 |
| Western Greece | 213 | 7.4 | 45.1 |
| Peloponnese | 78 | 3.7 | 18.7 |
| Epirus | 55 | 1.9 | 7.0 |
| Crete | 62 | 1.3 | 4.6 |
| Attica | 14 | 0.6 | 1.9 |
| Ionian Islands | 14 | 0.1 | 0.3 |
| South Aegean | 2 | 0.1 | 0.1 |
| Stations spanning two Regions | 4 | 0.2 | 0.7 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The Region is as ΡΑΑΕΥ records it for each station. A few stations span two Regions and are counted separately, in the last row.
ΑΔΜΗΕ publishes, twice a year, a register of the storage stations that have a connection offer or operate on the transmission system. The editions since May 2024 show the trend:
| Register edition | Stations | Injection power (GW) | Capacity (GWh) |
|---|---|---|---|
| May 2024 | 13 | 0.5 | 1.2 |
| October 2024 | 24 | 0.8 | 1.9 |
| April 2025 | 27 | 0.9 | 2.2 |
| October 2025 | 40 | 1.5 | 4.2 |
| April 2026 | 42 | 1.6 | 5.3 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The register covers the transmission system only. Stations connecting to ΔΕΔΔΗΕ's distribution network are not included.
| Month of issue | Stations | Injection power (GW) |
|---|---|---|
| July 2025 | 30 | 0.5 |
| August 2025 | 43 | 1.8 |
| September 2025 | 29 | 1.2 |
| October 2025 | 16 | 0.6 |
| November 2025 | 10 | 0.1 |
| December 2025 | 19 | 0.3 |
| February 2026 | 13 | 0.2 |
| March 2026 | 12 | 0.8 |
| April 2026 | 5 | 0.2 |
| May 2026 | 4 | 0.2 |
| June 2026 | 37 | 1.9 |
| July 2026 | 3 | 0.0 |
The table shows the twelve most recent months with issues, by the issue date the register records for storage stations. A month with no issues does not appear. The most recent issue date for a storage station in the register is 17 July 2026.
Quote these figures freely, with a link to this page. The HTML below holds the headline figures, their date and the source in one paragraph, ready for an article or a report.
<p>In ΡΑΑΕΥ's register, 1,580 electricity storage stations (65.3 GW of injection power) hold a storage licence; on the transmission system, 42 stations (1.6 GW) had a connection offer or were operating, according to ΑΔΜΗΕ's register (April 2026 edition). Source: <a href="https://ariadnelabs.eu/guides/greece-energy-storage-pipeline.html">Ariadne Labs, energy storage in Greece in numbers</a>, figures of 20 October 2026.</p>Once a month, one short email with the latest figures from this page and our other data pages, and what moved. To subscribe, write to hello@ariadnelabs.eu; to stop, reply "stop". Details are in the privacy notice.
The figures on this page describe the market. For your own projects, MitOS keeps each station's stage together with the deadlines and letters of guarantee that come with it. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.
A short demo on the real stages of your projects, with Greek law already built in.
In ΡΑΑΕΥ's register on 20 October 2026, 1,580 electricity storage stations, with 65.3 GW of injection power and 307.1 GWh of capacity.
On the transmission system, 42 stations, 1.6 GW, had a connection offer or were operating, according to ΑΔΜΗΕ's register (edition: April 2026). Stations on the distribution network are not included.
ΡΑΑΕΥ's register is checked daily and ΑΔΜΗΕ's files whenever a new edition is posted. The update date changes only when a figure changes.
This page presents aggregate figures from official files for information and does not replace legal or technical advice on a specific project. Each figure holds for the date given beside it. Only ΡΑΑΕΥ's and ΑΔΜΗΕ's own files are authoritative.