Standard Environmental Commitments (ΠΠΔ) for batteries were published on 10 October 2024. Since then, Greek Regions have issued 587 decisions including standalone storage stations under them, for 14.9 GW of injection power where the decision's subject states it. 473 were issued by 31 October 2025, the deadline of the merchant battery call, and 114 since.
Figures last updated: · Also in Greek: ΠΠΔ για μπαταρίες: πόσες αποφάσεις υπαγωγής εκδόθηκαν, ανά μήνα και Περιφέρεια
| Category | Decisions |
|---|---|
| Standalone storage station included under ΠΠΔ | 587 |
| of which: injection power below 1 MW | 5 |
| of which: 1 MW up to and including 10 MW | 306 |
| of which: above 10 MW | 266 |
| of which: no power in the subject | 10 |
| Amendment of an inclusion decision | 19 |
| Revocation of an inclusion decision | 9 |
| Renewable station with storage included (counted apart) | 61 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The power bands follow two rules. Below 1 MW of injection power no storage licence is needed. In the merchant battery call, ΔΕΔΔΗΕ granted the Final Connection Offer for stations up to and including 10 MW, and ΑΔΜΗΕ for larger ones.
| Month of issue | Inclusion decisions | Injection power (MW) |
|---|---|---|
| November 2024 | 9 | 294 |
| December 2024 | 19 | 486 |
| January 2025 | 22 | 391 |
| February 2025 | 35 | 1163 |
| March 2025 | 42 | 1051 |
| April 2025 | 42 | 1241 |
| May 2025 | 53 | 1414 |
| June 2025 | 51 | 846 |
| July 2025 | 51 | 1111 |
| August 2025 | 43 | 803 |
| September 2025 | 63 | 1781 |
| October 2025 | 43 | 856 |
| November 2025 | 14 | 290 |
| December 2025 | 9 | 187 |
| January 2026 | 5 | 293 |
| February 2026 | 13 | 309 |
| March 2026 | 13 | 165 |
| April 2026 | 15 | 276 |
| May 2026 | 11 | 476 |
| June 2026 | 12 | 170 |
| July 2026 | 8 | 468 |
| August 2026 | 2 | 111 |
| September 2026 | 4 | 135 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The table shows complete months. A month with no decisions does not appear. The busiest month was September 2025, with 63. The last twelve complete months saw 149, and the current month 8 so far. The most recent decision is dated 23 October 2026.
| Region | Inclusion decisions | Injection power (MW) |
|---|---|---|
| Central Greece | 122 | 4066 |
| Central Macedonia | 119 | 2212 |
| Western Macedonia | 106 | 2699 |
| Thessaly | 74 | 2035 |
| Eastern Macedonia and Thrace | 51 | 1727 |
| Western Greece | 30 | 661 |
| Epirus | 28 | 305 |
| Peloponnese | 26 | 624 |
| Crete | 19 | 479 |
| Ionian Islands | 10 | 46 |
| South Aegean | 2 | 50 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
The Region is the one that issued the decision. A Region that does not appear has not posted a decision on Diavgeia that meets the counting rule.
Category Β standalone battery stations do not need an environmental terms decision (ΑΕΠΟ). They are included under Standard Environmental Commitments set by ΥΠΕΝ/ΔΙΠΑ/103448/7298/2024 (Government Gazette Β΄ 5628/10.10.2024). The Region's environmental service issues the inclusion decision. It has no expiry date as long as the project's declared data do not change. The deadlines and the route are in the battery storage permitting guide.
Quote these figures freely, with a link to this page. The HTML below holds the headline figures, their date and the source in one paragraph, ready for an article or a report.
<p>Since Standard Environmental Commitments (ΠΠΔ) for batteries were published on 10 October 2024, Greek Regions have issued 587 decisions including standalone storage stations under them, for 14.9 GW of injection power where the decision's subject states it. Source: <a href="https://ariadnelabs.eu/guides/greece-battery-storage-environmental-approvals.html">Ariadne Labs, environmental approvals for battery storage in Greece</a>, from decisions published on Diavgeia, figures of 26 October 2026.</p>Once a month, one short email with the latest figures from this page and our other data pages, and what moved. To subscribe, write to hello@ariadnelabs.eu; to stop, reply "stop". Details are in the privacy notice.
The figures on this page describe the market. For your own projects, MitOS keeps each station's stage together with the deadlines and letters of guarantee that come with it. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.
A short demo on the real stages of your projects, with Greek law already built in.
From 10 October 2024 to 26 October 2026, Greek Regions issued 587 decisions including standalone storage stations under Standard Environmental Commitments, for 14.9 GW of injection power where the subject states it.
Central Greece, with 122 inclusion decisions as of 26 October 2026. The full ranking is in the table by Region.
No. It stays valid with no expiry date as long as the declared data do not change (ΥΠΕΝ/ΔΙΠΑ/103448/7298/2024, art. 5(1)).
This page presents aggregates of public decisions for information and does not replace legal or technical advice on a specific project. Classification works from each decision's subject and can miss decisions worded unusually. Only the decisions as posted on Diavgeia are authoritative.