Tool · Greece

Guarantee exposure calculator: what a Greek energy project has at stake

A Greek solar, wind or battery project ties up money in letters of guarantee long before it earns anything. A 50 MW solar plant with a Final Connection Offer and a place in an ΑΔΜΗΕ priority group, for example, has EUR 5,237,300 lodged: EUR 237,300 for the connection offer and EUR 5,000,000 for priority. Enter your own project below to see what is lodged, what releases or forfeits each guarantee, and what a delay costs. Nothing you type leaves your browser.

Last updated: · Also in Greek: Υπολογιστής εγγυητικών επιστολών: τι διακυβεύεται σε ένα ενεργειακό έργο

Which guarantees apply now?
GuaranteeAmountRelease or forfeitureProvision
Producer certificateEUR 35,000 per MWreturned when a complete request for a Final Connection Offer is filedLaw 4685/2020, art. 11A
Final Connection Offer30% of EUR 42, 21, 14 and 7 per kW by bandforfeited if not renewed in time, or if no connection contract takes effect while the offer is validLaw 4951/2022, arts. 6 and 89A
Priority (ΑΔΜΗΕ groups Α, Β, Δ and Π9)EUR 100,000 per MWhalved on the connection contract, returned on operationΥΠΕΝ/ΓΔΕ/84014/7123/2022, art. 6
Bilateral agreement (Group Β)EUR 100,000 per MWforfeited if the signed agreement is not filed within 9 months of the offersame decision, arts. 2 and 7
Proper and timely performance, ΡΑΑΕΥ storage tendersEUR 250,000, 150,000 or 200,000 per MWforfeited in full without a connection activation request by 15.12.2026Law 5233/2025, art. 43(1), as amended by Law 5338/2026
Standalone storage, 2025 callEUR 200,000 per MW above 10 MW, EUR 50,000 up to 10 MWthe performance and operation guarantee is halved after 3 years of operation and returned after 6ΥΠΕΝ/ΓΔΕ/28255/1143/2025, as amended
Total lodged
Bank fees over the delayyour rate, on the total lodged
Revenue pushed back by the delayyour revenue estimate

How the calculator works

How MitOS sees it

MitOS maps the guarantees per technology: which guarantees, to whom, how much, by when. Contracts, guarantees and invoices sit on the same record as the permits, so an expiring guarantee is a project risk, not a surprise. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.

See it on your own portfolio

Request a short, focused demo on the real stages of your projects, with every guarantee and deadline in one place.

Frequently asked questions

How much is the connection guarantee for a 50 MW solar plant in Greece?

The scale of art. 6 of Law 4951/2022 gives EUR 791,000, of which 30%, EUR 237,300, is lodged since 31 October 2024.

How much does an ΑΔΜΗΕ priority group add?

EUR 100,000 per MW of maximum generation or injection capacity, or EUR 5,000,000 for a 50 MW plant. It is halved when the connection contract takes effect and returned when the plant enters operation.

Is the producer certificate guarantee returned?

Yes. The EUR 35,000 per MW is returned when the complete request for a Final Connection Offer is filed.

The calculator is indicative and does not replace legal or financial advice on a specific project. Amounts are those of the provisions cited, as in force on the date at the top.