The Swiss Federal Office of Energy (SFOE) lists 29 large solar projects, 28 of them in the procedure or in operation, designed for 425.5 MW and 645.8 GWh a year. Of these, 7 have a legally binding approval or are already running, with 115.6 GWh a year: 5.8% of the 2 TWh up to which art. 71a of the Energy Act applies.
Figures last updated: · Latest status report in the SFOE data: 10 September 2026 · Also in German: Solarexpress: Wo die Photovoltaik-Grossanlagen nach Art. 71a EnG stehen
| Status | Projects | Capacity (MW) | Annual production (GWh) | of which winter half-year (GWh) |
|---|---|---|---|---|
| building application on public display | 11 | 256.7 | 388.9 | 173.0 |
| approved at first instance | 10 | 90.6 | 141.2 | 57.5 |
| approval legally binding | 3 | 32.1 | 45.8 | 19.2 |
| partly in operation | 4 | 46.1 | 69.8 | 30.3 |
| fully in operation | 0 | 0.0 | 0.0 | 0.0 |
| in operation for 3 years | 0 | 0.0 | 0.0 | 0.0 |
| withdrawn | 1 | 9.4 | 12.0 | 5.3 |
| rejected | 0 | 0.0 | 0.0 | 0.0 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
Each project counts with the latest status the SFOE records for it, and with the capacity and production reported at that status. For plants only partly in operation, that is the planned capacity, not the part already built. 4 plants are partly in operation and 0 fully.
The eased permitting conditions of art. 71a apply only as long as an annual production of 2 TWh across Switzerland from plants with a legally binding approval is not expected to be reached. The 7 plants with a legally binding approval, or already running, add up to 115.6 GWh a year. Even if all 28 projects were built, they would produce 645.8 GWh, 32.3% of the threshold.
Little can be added now. Art. 71a covers only plants whose building application was put on public display by 31 December 2025, and the most recent public display in the SFOE data is dated 18 December 2025.
| Quarter of public display | Projects | Capacity (MW) |
|---|---|---|
| Q4 2023 | 3 | 61.1 |
| Q1 2024 | 5 | 51.7 |
| Q2 2024 | 6 | 146.5 |
| Q3 2024 | 2 | 19.4 |
| Q4 2024 | 2 | 15.6 |
| Q1 2025 | 2 | 16.5 |
| Q2 2025 | 3 | 47.3 |
| Q3 2025 | 1 | 6.2 |
| Q4 2025 | 5 | 70.6 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
Each project counts in the quarter of its first public display, even if it was later withdrawn. The capacity is the one reported today.
| Canton | Projects | Capacity (MW) | Annual production (GWh) | of which legally approved or in operation (projects) |
|---|---|---|---|---|
| Valais | 12 | 237.3 | 374.8 | 0 |
| Graubünden | 9 | 124.7 | 182.9 | 6 |
| Bern | 4 | 36.9 | 50.3 | 0 |
| Ticino | 2 | 18.5 | 26.6 | 0 |
| Uri | 1 | 8.0 | 11.2 | 1 |
This table as data: CSV · JSON · free to reuse with attribution (CC BY 4.0)
Valais has the most projects, 12. Withdrawn and rejected projects are not in this table. 20 of the 28 projects lie at 2,000 metres or higher, and the winter half-year accounts for 43.4% of their planned annual production.
The provision was added to the Energy Act by the urgent federal act of 30 September 2022 and is known as the "Solarexpress". The version in force rests on the federal act of 21 March 2025 on building planned alpine solar plants and has applied since 1 January 2026.
Quote these figures freely, with a link to this page. The HTML below holds the headline figures, their date and the source in one paragraph, ready for an article or a report.
<p>Large solar projects under art. 71a of the Swiss Energy Act (the Solarexpress) with a legally binding approval or already in operation account for 115.6 GWh a year, 5.8% of the 2 TWh up to which the article applies; 28 projects, designed for 645.8 GWh a year, are in the procedure or in operation. Source: SFOE, compiled by <a href="https://ariadnelabs.eu/guides/solarexpress-switzerland-alpine-solar.html">Ariadne Labs</a>, figures of 21 October 2026.</p>Once a month, one short email with the latest figures from this page and our other data pages, and what moved. To subscribe, write to hello@ariadnelabs.eu; to stop, reply "stop". Details are in the privacy notice.
The figures on this page describe the market. In Switzerland MitOS covers every technology it offers, from large solar plants to carbon capture. For your own projects, MitOS keeps each plant's stage together with the deadlines and guarantees that come with it. A rolling 90-day timeline and a live flag feed surface what is due and what is at risk before it costs you the project.
Request a short, focused demo on the real stages of your projects.
According to the SFOE data, 4 plants are partly and 0 fully in operation.
7, counting those already running, with 78.2 MW and 115.6 GWh a year between them. A further 10 are approved at first instance but not yet with legal force.
Only to plants whose building application was on public display by 31 December 2025, and only while the 2 TWh threshold from plants with a legally binding approval is not expected to be reached.
The canton, with the consent of the host municipality and the landowners.
Valais, with 12 projects in the procedure or in operation.
This page summarises SFOE data for information and does not replace legal or permitting advice on a specific project. Each figure holds for the date given. Only the SFOE data and the official publication of the Energy Act are authoritative.